We were contracted for the consultancy, construction management and commissioning of two Water Treatment Plants (WTP) in Dondo, Angola. Each plant has a production capacity of 20 m³/h. Our work included supervision of assembly, installation, operator training and commissioning of the units.
The project included the execution of several works:
To ensure the correct operation of the plants, we train the operators in several aspects:
Finally, for start-up, we perform laboratory tests to determine the quality of the raw water and the optimum coagulant dosage. We also regulate the flow rate and perform field tests of the treated water to adjust the dosage of the chemicals.
This project allowed us to contribute to improving access to drinking water in the community of Dondo, guaranteeing its long-term operation through the training of local personnel.